As part of Computershare’s ongoing efforts to minimise our already small impact on the environment, we have set reduction targets at our key sites around the world covering general waste, electricity, natural gas and water (where data is available). You can view our progress in these areas via the following links:

2019-20 tar​gets
2021-22 targets
2022-23 targets

Our sustainability targets are set in the following areas:

  • Waste

  • Electricity

  • Gas

  • Water

FY2020 Targets - complete

In FY2015 we implemented our second phase of 5-year reduction targets in Canton in Massachusetts, USA; Munich in Germany; Auckland in New Zealand; and Hong Kong.

We have met our target for Auckland.

Our offices in Munich, Canton and Hong Kong have since relocated. We set a new target for Munich in FY2018. New targets will be set for Canton and Hong Kong after stable baselines are in place at these new locations.

Back to top ​​​​

Auckland, New Zealand

  • On target

    Baseline: 324kWh/FTE FY20 actual: 106kWh/FTE Target: 258kWh/FTE

Back to top ​​​​

Canton, USA (office has relocated)

  • On target

    Baseline: 1348kWh/FTE FY18: 1287kWh/FTE Target: 1294kWh/FTE

  • In progress

    Baseline: 88mJ/FTE FY18: 104mJ/FTE Target: 87mJ/FTE

  • In progress

    Baseline: 0.9kl FY18: 1.2kl Target: 0.8kl

Ba​ck to top ​​​​

Hong Kong (office has relocated)

  • In progress

    Baseline: 43kWh/FTE FY18: 40.9kWh/FTE Target: 40.7kWh/FTE

Back to top ​​​​

Munich, Germany (office has relocated)​​

  • Target met

    Baseline: 282kWh/FTE FY16: 133kWh/FTE Target: 254kWh/FTE

FY2022 Targets - with two years to go

During FY2018 we introduced new targets at four of our locations in the UK and set a new target for our office in Munich, which relocated during FY2017.​

Doxford, UK

  • In progress

    Baseline: 12.8kWh/SQM FY20: 13.4kWh/SQM Target: 12.2kWh/SQM

  • In progress

    Baseline: 32.1mJ/SQM FY20: 29.4mJ/SQM Target: 30.5mJ/SQM

Crossflatts, UK

  • On target

    Baseline: 13.5kWh/SQM FY20: 12.9kWh/SQM Target: 12.9kWh/SQM

  • In progress

    Baseline: 17.8mJ/SQM FY20: 26.1mJ/SQM Target: 16.9mJ/SQM

Halifax, UK

  • On target

    Baseline: 3.5kWh/SQM FY20: 2.6kWh/SQM Target: 3.3kWh/SQM

Munich, Germany (new office)

  • In progress

    Baseline: 5.2kWh/SQM FY20: 5.2kWh/SQM Target: 4.9kWh/SQM

Skipton, UK

  • On target

    Baseline: 23.8kWh/SQM FY20: 19.6kWh/SQM Target: 22.6kWh/SQM

  • In progress

    Baseline: 13.9mJ/SQM FY20: 9.4mJ/SQM Target: 13.2mJ/SQM

FY2023 Targets - with three years to go

In FY2018 we completed our first set of five-year reduction targets across some of our largest locations. We met 9 of 16 of these targets.

Even where we didn’t meet the targets, we made substantial progress in all areas of gas, electricity and water consumption as well as waste reduction.

We have now set new targets at these locations, with the aim of achieving a further 5% reduction on our FY18 data over a five-year period.

Back to top ​​​​

Bristol, United Kingdom

  • On target

    Baseline: 1.3kg/FTE FY20: 1.3kg/FTE Target: 1.2kg/FTE

  • In progress

    Baseline: 22.4kWh/SQM FY20: 20.7kWh/SQM Target: 21.3kWh/SQM

  • In progress

    Baseline: 12.3mJ/SQM FY20: 19.2mJ/SQM Target: 11.7mJ/SQM

  • In progress

    Baseline: 0.57kl/FTE FY20: 0.55kl/FTE Target: 0.54kl/FTE

Back to top ​​​​

East Beaver Creek, Canada

  • On target

    Baseline: 6.4kg/FTE FY20: 6.4kg/FTE Target: 6.1kg/FTE

  • In progress

    Baseline: 29.5kWh/SQM FY20: 47.6kWh/SQM Target: 28.0kWh/SQM

  • On target

    Baseline: 124.8mJ/SQM FY20: 97.5mJ/SQM Target: 118.5mJ/SQM

  • On target

    Baseline: 1.12kl/FTE FY20: 1.01kl/FTE Target: 1.06kl/FTE

Back to top ​​​​

Bolingbrook, USA

  • On target

    Baseline: 19.0kWh/SQM FY20: 24.2kWh/SQM Target: 18.0kWh/SQM

  • On target

    Baseline: 17.6mJ/SQM FY19: 16.6mJ/SQM Target: 16.7mJ/SQM

​​​​

Melbourne, Australia

  • On target

    Baseline: 8.5kg/FTE FY20: 2.8kg/FTE Target: 8.1kg/FTE

  • On target

    Baseline: 18.1kWh/SQM FY20: 15.7kWh/SQM Target: 17.2kWh/SQM

  • In progress

    Baseline: 17.0mJ/SQM FY20: 21.2mJ/SQM Target: 16.1mJ/SQM

  • In progress

    Baseline: 0.63kl/FTE FY20: 0.72kl/FTE Target: 0.60kl/FTE